On one of the most frequented avenues in the core of Scotland's ancient city stands a giant structure of scaffolding.
For five years, the establishment on the junction of a key historic street and the adjacent bridge has been a covered eyesore.
Visitors cannot book rooms, foot traffic are funneled through confined passages, and businesses have vacated the building.
Remedial work commenced in 2020 and was only expected to last a few months, but now exasperated residents have been told the framework could stay in place until 2027.
The main contractor, the lead company, says it will be "towards the end" of 2026 before the earliest portions of the frame can be taken down.
A local authority figure a city representative has described it as a "negative feature" on the area, while heritage campaigners say the work is "highly inconvenient".
What is transpiring with this apparently perpetual project?
The 136-bedroom hotel was built on the site of the old regional authority offices in 2009.
Estimates from when it originally launched under the a designer banner, put the build cost at about thirty million pounds.
Work on the building began soon after the start of the coronavirus outbreak with the hotel itself closed to guests since 2022.
A section of the street and a sizable stretch of pavement leading up to the intersection of the historic street have been closed off by the work.
People on foot going to and from the an adjacent district and another locale have been forced single-file into a narrow, covered walkway.
An eatery Ondine departed from the building and relocated to another city in 2024.
In a comment, its operators said building work had forced them to alter the restaurant's appearance, adding that "patrons merited more".
It is also hosts popular eatery a chain – which has hung large banners on the structure to inform customers it is open for business.
An report to the a city committee in the start of the year suggested that the process of "revealing" the façade would begin in February, with a total takedown by the end of the year.
But the firm has said that is not the case, referencing "highly complicated" structural challenges for the postponement.
"We expect starting to remove sections of the scaffold close to the conclusion of 2026, with additional work proceeding afterwards," they said.
"We are collaborating closely with all parties to ensure we create an better site for the public."
Rowan Brown, director of preservation association the Cockburn Association, said the work had contributed to the city's reputation of being "slow" for development.
She said those working on the project had a "civic responsibility" to reduce inconvenience and should incorporate the work into the city's streetscape.
She said: "It causes the walking experience in that area of the city exceptionally challenging.
"I don't understand why there is not a try to integrate it into the street view or create something more creative and innovative."
A official statement said work on "measures to aesthetically improve the site" was in progress.
They continued: "We acknowledge the irritations felt by local residents and businesses.
"This constitutes a extended and complex process, highlighting the complexity and magnitude of the remedial work required, however we are focused on completing this essential work as soon as is practicable."
The council leader said the local authority would "continue to put pressure" on those responsible to complete the project.
She said: "This scaffolding has been a problem for years, and I understand the annoyance of residents and area enterprises over these continued delays.
"That said, I also recognize that the company has a responsibility to make the building structurally sound and that this remediation has turned out to be hugely complex."
A seasoned casino analyst with over a decade of experience in gaming strategies and industry insights.